Notice to Proceed (“NTP”)

March 15, 2021

 

March 3, 2025

Design

Phase 1 & 2

Design Public Information Workshops
Summer 2021, Winter 2022, Winter 2023

Phase 1 & 2

Design, Permitting, Bid + Award

Summer 2021 to Winter 2023/2024

Phase 1 - NW/NE 17th St to North of NW 25th Ct (City Limits)

Phase 2 - North of Lake Ida Rd to South of NW/NE 17th St

Construction

Phase 1

Construction

October/November 2024 through October/November 2025

Public Information Workshop

September 2024

Phase 2

Construction 

October/November 2025 through October/November 2026

Public Information Workshop 

August/September 2025